Construction UK Construction Directory
Time and date
CONSTRUCTION DIRECTORY
Share this page
Construction News
05/04/2013

World's Second Deepest Sewage Treatment Works Takes Shape In Jeddah

Construction News Image
Contractor Abuljadayel Co., specialists in the field of water and waste water projects, has utilised a number of formwork and shoring solutions provided by RMD Kwikform to support the construction of the World's second deepest pumping station at the North Jeddah Pumping Station project in Saudi Arabia.

Designed to deal with the increased demands of the growing population of Jeddah, the new facility is part of a $1.1bn investment programme funded by Saudi Arabia's National Water Company. The North Jeddah pumping station facility comprises of a screen shaft and two pumping shafts, all of which drop over 72 metres in total into the ground. There is also a three-stage collection chamber, various auxiliary buildings and permanent site offices.

Each shaft is 68 metres deep. The screen shaft has a 4.5 metre thick concrete base slab and each pumping shaft has a 5.5 metre thick base slab. Before RMD Kwikform started supplying formwork, the contractor constructed the circular diaphragm walls using 2.4 metre concrete panels. Once excavated to full depth, the 1.2 metre shaft thick wall was constructed, followed in succession by the bottom slab.

There were three main formwork elements of the project that RMD Kwikform was involved in, including supplying double-sided wall formwork to the U-shaped Collection Chamber building. Using a range of equipment, including steel Superslim Soldiers as primary beams and Alform beams as secondaries, the wall formwork reached a total height of 13 metres. With 348 linear metres of equipment being used for this section of the construction, the entire structure above ground level was poured in a single pour, using a total volume of 3,100m3 of concrete.

Rapidshor shoring with U-heads and Alform beams were also used to support 500mm thick concrete slabs on top of the three 46 metre diameter shafts. The Rapidshor was built 68 metres high and topped with U-heads, which held double Alform beams as primary bearers and single Alform beams as secondaries.

Commenting on the project, Mohammed Asif from RMD Kwikform said: "When we were faced with the shoring challenge of supporting a slab 68 metres high, but underground in a confined space with very little room to play with, we recognised there were two key hurdles to the project, the first being safety and the second logistics. Having had previous experience using Rapidshor on major bridge projects, we knew the equipment was structurally capable of dealing with the load, and due to it being a modular system, installation was more straightforward within the confines of the shafts."

-- Advertisement --
hss

In order to support the slab construction, each shaft was lined with over 10,255m3 of Rapidshor shoring. This was built up into a birdcage structure, securely tied into the main concrete walls and laced together to form a shoring solution capable of supporting the construction of drop beams and the capping slab of each shaft.

The 2,000mm deep, 600mm wide, 5,000mm long drop beams were constructed using Superslim Soldier primary beams and Alform secondary beams, with the slab support constructed using Alform beams. The 500mm deep capping slabs were then poured in order to partially cover the shafts. The cover slabs will go on to form part of the ground floor of permanent site offices, due to be built towards the end of the project.

Mohammed Asif continued: "The main engineering challenge was how to tie the system together and install safe access for the workers. It was for this reason that as part of the solution we supplied onsite technical assistance in the shape of two site operatives. One of the technicians remained onsite with the ground team from start to finish, with an additional team member supporting the training and erection programme devised for the customer."

The third part of the construction that RMD Kwikform assisted with was to supply a Rapidclimb and Maxima wall formwork panel system for the 500mm thick internal walls, required for the lift core walls, stairwells and offices for two of the shafts. In order to provide an efficient and safe solution, RMD Kwikform recommended a combination of Maxima modular wall formwork and Rapidclimb climbing formwork. The panel system approach was specified by the contractor, having seen the capabilities of Maxima.

The RMD Kwikform Rapidclimb system was used inside two of the pumping shafts to provide wall formwork to the lift-shaft cores and internal walls. Rapidclimb is a crane assisted climbing formwork system that provides safe, self-contained working levels for economical core and wall forming. It also features a rack and pinion activated mechanism with a wedge-locking device for securing the position of the shutter. The climbing bracket can achieve up to 45kN maximum vertical capacity.

Mohammed Asif commented: "When we were faced with the core formwork challenge, we saw it as an opportunity to utilise the capabilities of Maxima as the wall formwork system. It has been used extensively in similar projects across the globe, so we were confident it was the right solution to overcome the challenges posed by this project.

"By reusing the Maxima panels for each of the 24 pours required for the formation of the core, significant time and cost saving benefits were realised. Mohammad Rateb Jawish from Abuljadayel Co. said: "The tight programme time required us to think carefully about the solution we required for the formwork and shoring parts of the project. Using a modular panel system, such as Maxima allowed us to complete the whole core construction efficiently and to a high quality standard. The time and cost saving benefit we saw certainly showed the advantages of utilising a panel systems on this type of project."

Construction is expected to be completed in June 2013. Once operational, the Pumping station is designed to pump a maximum flow of 1,125,000m3 per day, ensuring enough capacity to cope with future predictions for population growth.

formula.rmdkwikform.com

Latest Construction News

29/11/2024

Helmsley Group secured planning permission for the final part of its Coney Street Riverside masterplan which will bring much needed residential space to the city and realise a 50-year ambition to reconnect York to its riverfront. With work expected to start in the summer of 2025, this approval ...
29/11/2024

Network Space Developments (NSD) has received planning approval from Manchester City Council for a major redevelopment project at its Welcomb Street site in Openshaw, Manchester. The four-acre site, acquired by NSD in 2022, will be transformed into an extension of the adjacent City Works Business ...
29/11/2024

Work has commenced on a new lighting scheme designed to create brighter streets in Digbeth, close to HS2's Birmingham Curzon Street station. The Birmingham City Council project – funded in part through a £210,140 investment from HS2's Business and Local Economy Fund (BLEF) – will see the ...
29/11/2024

Building work has commenced on 14 new modern one-bedroom apartments at Ludwick Green in Welwyn Garden City. The apartments are being developed as part of Welwyn Hatfield Borough Council's (WHBC) Affordable Housing Programme, and its commitment to building new social and affordable homes. Ludwick ...
29/11/2024

River Capital has invested £500,000 in Liverpool-based M&E engineering consultancy, Steven A Hunt & Associates Ltd. The funding was structured to facilitate a management buyout (MBO) by the senior management team of Neil Baines, Anne King, Dave Kelly and Dominic Sibbring from founder Steven Hunt, ...
29/11/2024

Henley Restoration and Remedials has been chosen to carry out extensive external and structural repairs on the Grade II-listed Phoenix Mill, the oldest building in the Rutland Mills complex. Originally a grain store, Phoenix Mill later became a corn mill in the 19th century before transitioning ...
29/11/2024

Dorset County Council's North East Technology Park (NETPark) has been allocated over £11 million towards its expansion. The North East Combined Authority's Cabinet has approved £11.3m of funding for the Sedgefield site from its £160m flagship North East Investment Zone (NEIZ), which aims to drive ...
29/11/2024

Laing O'Rourke, in collaboration with Barnsley College and T3 Training & Development, have opened the UK's first dedicated modern methods of construction (MMC) training facility. The first of its kind training centre represents a groundbreaking step in addressing the UK's construction skills ...
29/11/2024

Aqua Direct are keen to share their support for the Urgent Funding campaign from St Giles Hospice. With a national hospice funding crisis, they need your support more than ever ...
29/11/2024

As we approach the end of 2024, we have been reflecting on what an action-packed year it has been. We have worked with some fantastic clients and sites across the country. We started from our base in Essex over ten years ago, and the demand for trackway has certainly been at its highest ...
T & D Glazing And Installation LimitedStuart CanvasBRICOFLOR UKLakeside HireAqua Direct LtdThink Construction Skills Ltd.Efco UK LtdSmart Trade Shop LtdAccess Control Solutions (UK) LimitedCAN Structures Ltd
Terms and Conditions
2024/11/29 21:24:45