24/04/2014

Costain Completes Waste Work One Year Early

Costain has completed work on the refurbishment of Severn Trent Water (STW)'s Kineton waste water treatment plant near Coventry twelve months ahead of schedule.

The Kineton Q project involved revamping the site’s process assets to enable it to comply with lower EU ammonia discharge consent levels. These do not come into force until March 2015, however there was a small risk that the chosen solution might not deliver the required outputs to satisfy the new consent. The STW/Costain team decided to take a risk based approach and carry out the work as early as possible so it had time to react if the scheme was unsuccessful. In order to undertake the refurbishment work the process would have needed temporary treatment units to help prop up the site whilst the NSAF (Nitrifying Submerged Aeration Filter) was out of commission. However the team made use of the seasonal relaxation of consent levels for this site from November to April to undertake the work, so that no temporary treatment was required.

-- Advertisement --
hss

Richard Price, Costain Programme Manager, said: "The Environment Agency relaxes consents for some sites in the winter when conditions are wetter and the concentration of ammonia in the waste is lower. In summer, conditions tend to be drier, the concentrations higher and so the consent is tighter.

"Carrying out the work in winter meant we did not have to install a temporary filter. Instead we just had to isolate the NSAF while we refurbished the plant’s media. This new approach allowed us to complete the physical works in less than a week, saving us a significant amount of time. Because the work was completed a year early we could also trial a lower cost option that did carry some risk of failure. We had the time to react if the solution did not work."

By assisting the Severn Trent Water process engineers with sampling and testing, the Costain team was able to handover the process in less than two months.

(CD)

Latest Construction News

29/11/2024

Helmsley Group secured planning permission for the final part of its Coney Street Riverside masterplan which will bring much needed residential space to the city and realise a 50-year ambition to reconnect York to its riverfront. With work expected to start in the summer of 2025, this approval ...
29/11/2024

Network Space Developments (NSD) has received planning approval from Manchester City Council for a major redevelopment project at its Welcomb Street site in Openshaw, Manchester. The four-acre site, acquired by NSD in 2022, will be transformed into an extension of the adjacent City Works Business ...
29/11/2024

Work has commenced on a new lighting scheme designed to create brighter streets in Digbeth, close to HS2's Birmingham Curzon Street station. The Birmingham City Council project – funded in part through a £210,140 investment from HS2's Business and Local Economy Fund (BLEF) – will see the ...
29/11/2024

Building work has commenced on 14 new modern one-bedroom apartments at Ludwick Green in Welwyn Garden City. The apartments are being developed as part of Welwyn Hatfield Borough Council's (WHBC) Affordable Housing Programme, and its commitment to building new social and affordable homes. Ludwick ...
29/11/2024

River Capital has invested £500,000 in Liverpool-based M&E engineering consultancy, Steven A Hunt & Associates Ltd. The funding was structured to facilitate a management buyout (MBO) by the senior management team of Neil Baines, Anne King, Dave Kelly and Dominic Sibbring from founder Steven Hunt, ...
29/11/2024

Henley Restoration and Remedials has been chosen to carry out extensive external and structural repairs on the Grade II-listed Phoenix Mill, the oldest building in the Rutland Mills complex. Originally a grain store, Phoenix Mill later became a corn mill in the 19th century before transitioning ...
29/11/2024

Dorset County Council's North East Technology Park (NETPark) has been allocated over £11 million towards its expansion. The North East Combined Authority's Cabinet has approved £11.3m of funding for the Sedgefield site from its £160m flagship North East Investment Zone (NEIZ), which aims to drive ...
29/11/2024

Laing O'Rourke, in collaboration with Barnsley College and T3 Training & Development, have opened the UK's first dedicated modern methods of construction (MMC) training facility. The first of its kind training centre represents a groundbreaking step in addressing the UK's construction skills ...
29/11/2024

Aqua Direct are keen to share their support for the Urgent Funding campaign from St Giles Hospice. With a national hospice funding crisis, they need your support more than ever ...
29/11/2024

As we approach the end of 2024, we have been reflecting on what an action-packed year it has been. We have worked with some fantastic clients and sites across the country. We started from our base in Essex over ten years ago, and the demand for trackway has certainly been at its highest ...
Stuart CanvasEfco UK LtdThink Construction Skills Ltd.Lakeside HireT & D Glazing And Installation LimitedAqua Direct LtdBRICOFLOR UKA.J. Brockwitz & SonsCP Cases LtdModel Signage Solutions
Terms and Conditions
2024/11/29 21:26:15