A major jump in the cost of electrifying the Great Western Main Line has been described as "staggering and unacceptable" by Ministers.
In a new report, the Public Accounts Committee said the £1.2 billion increase in the cost of the programme has raised concerns over the ability of the Department for Transport and Network Rail to manage similar future schemes, such as the planned electrification of the Midland Main Line and TransPennine routes.
The Committee said an examination of Network Rail's 2015 investment programme to find the extent of failings on the project, which led to cost overruns and a three-year delays, "are now clearer".
However, doubts remain over whether the scheme can still be delivered on a £2.8 budget by December 2018.
Meg Hillier MP, Chair of the PAC, said: "Mismanagement of the Great Western programme has hit taxpayers hard and left many people angry and frustrated.
"This is a stark example of how not to run a major project, from flawed planning at the earliest stage to weak accountability and what remain serious questions about the reasons for embarking on the work in the first place.
"The sums of public money wasted are appalling—not least the £330 million additional costs the Department for Transport will have to pay to keep the trains running because of delays to electrification.
"The Department failed to adequately challenge Network Rail's plans to carry out the infrastructure work and, even now, casts doubt on whether electrification work on this and other lines is even necessary."
In its recommendations, the PAC said Network Rail must improve its ability to produce realistic cost estimates and make sure that robust and detailed plans are in place for infrastructure projects before starting construction.
In addition, the DfT must ensure suitable assurance is in place before taking decisions on infrastructure investment "and other major decisions which depend on infrastructure being available". The Department should also reassess the case for electrification section-by-section and fund schemes "only where worthwhile benefits for passengers could not be achieved otherwise at lower cost".
The two organisations must also plan developments to rail services in a way which brings together trains, infrastructure work and the operation of services, obtaining independent assurance on their plans.
Overall, both the Department and Network Rail accept that there were significant failings in the design, planning and cost-estimating of the programme.
Ms Hillier continued: "Government accepts it got this project badly wrong and must now demonstrate it has learned the lessons.
"Network Rail admits there are still very significant risks in the Great Western scheme and it is vital these are fully identified and carefully managed.
"It must work with the Department to ensure this information is properly factored into the whole rail modernisation programme.
"For its part, the Department should urgently review its plans for electrification—not just on the different sections of the Great Western route, but also on the Midland Main Line and TransPennine routes.
"Electrification was heralded with the promise of benefits to passengers but the Government has a duty to determine if, in fact, these benefits can be delivered in a more timely and cost-effective way."
(LM/MH)
Time and date
CONSTRUCTION DIRECTORY
Construction News
03/03/2017
MPs Slam Rocketing Cost Of Great Western Main Line Electrification
Latest Construction News
29/11/2024
Helmsley Group secured planning permission for the final part of its Coney Street Riverside masterplan which will bring much needed residential space to the city and realise a 50-year ambition to reconnect York to its riverfront. With work expected to start in the summer of 2025, this approval ...
29/11/2024
Network Space Developments (NSD) has received planning approval from Manchester City Council for a major redevelopment project at its Welcomb Street site in Openshaw, Manchester. The four-acre site, acquired by NSD in 2022, will be transformed into an extension of the adjacent City Works Business ...
29/11/2024
Work has commenced on a new lighting scheme designed to create brighter streets in Digbeth, close to HS2's Birmingham Curzon Street station. The Birmingham City Council project – funded in part through a £210,140 investment from HS2's Business and Local Economy Fund (BLEF) – will see the ...
29/11/2024
Building work has commenced on 14 new modern one-bedroom apartments at Ludwick Green in Welwyn Garden City. The apartments are being developed as part of Welwyn Hatfield Borough Council's (WHBC) Affordable Housing Programme, and its commitment to building new social and affordable homes. Ludwick ...
29/11/2024
River Capital has invested £500,000 in Liverpool-based M&E engineering consultancy, Steven A Hunt & Associates Ltd. The funding was structured to facilitate a management buyout (MBO) by the senior management team of Neil Baines, Anne King, Dave Kelly and Dominic Sibbring from founder Steven Hunt, ...
29/11/2024
Henley Restoration and Remedials has been chosen to carry out extensive external and structural repairs on the Grade II-listed Phoenix Mill, the oldest building in the Rutland Mills complex. Originally a grain store, Phoenix Mill later became a corn mill in the 19th century before transitioning ...
29/11/2024
Dorset County Council's North East Technology Park (NETPark) has been allocated over £11 million towards its expansion. The North East Combined Authority's Cabinet has approved £11.3m of funding for the Sedgefield site from its £160m flagship North East Investment Zone (NEIZ), which aims to drive ...
29/11/2024
Laing O'Rourke, in collaboration with Barnsley College and T3 Training & Development, have opened the UK's first dedicated modern methods of construction (MMC) training facility. The first of its kind training centre represents a groundbreaking step in addressing the UK's construction skills ...
29/11/2024
Aqua Direct are keen to share their support for the Urgent Funding campaign from St Giles Hospice. With a national hospice funding crisis, they need your support more than ever ...
29/11/2024
As we approach the end of 2024, we have been reflecting on what an action-packed year it has been. We have worked with some fantastic clients and sites across the country. We started from our base in Essex over ten years ago, and the demand for trackway has certainly been at its highest ...