Extract from a paper by David Scopes IEng MICE, Engineer at Atkins Ltd, Peterborough.
The market town of Louth, on the River Lud, has suffered from flooding on many occasions, most recently in 2007. Atkins was commissioned to conduct a feasibility study into the viability of a flood defence scheme.
This paper begins once the preferred option of two online flood storage areas was identified; the brief from this point was to develop their outline design. The maximum allowable outflow (to prevent flooding) for each storage area had been calculated as a part of the preceding hydrological study, and therefore was known at the start of the design. The exact volume of storage, being dependent on the method of controlling flows, had at this stage been calculated assuming no additional flows were impounded.
The control structure design of the project required a balance of two factors: maintenance and storage. Using options with no moving parts (fixed weir, orifice, vortex type flow control etc.), which solely limit the flow, result in increased storage, but are able to offer very low maintenance costs. Conversely, low storage can be achieved through the use of a mechanical and electrical setups, however these would have significant maintenance costs and potential reliability issues. Accepting some moving parts, and therefore some maintenance, allowed the Eliquo Hydrok HydroSlide to be considered.
A HydroSlide consists of a see-saw on a pivot with a plate at one end and a float as the counter balance at the other. As the water level increases the float rises causing the plate to close across the orifice opening and restricting outflow. Although it has a moving part, the discharge curve holds tightly to the optimum discharge, plus or minus five percent.
The other advantage of the HydroSlide is that it is adjustable by up to 30% during an event (via a spindle) to increase or reduce flows as required. This means that if the actual downstream maximum allowable flow is found to be different than that predicted by the mathematical model due to insufficient data, a change in the structures, or a blockage, the problem could be overcome without having to wait for the flood to subside.
The ability to provide the more refined level of flow control, with relatively little maintenance, and the advantage of post-construction in-event adjustment led to the HydroSlide being adopted.
To discuss how the Eliquo Hydrok HydroSlide solutions, contact Dave Armstrong on 01726 861900, or email dave.armstrong@eliquohydrok.co.uk
www.hydrok.co.uk
Time and date
CONSTRUCTION DIRECTORY
Construction News
16/05/2017
Eliquo Hydrok HydroSlide Used For Louth Flood Alleviation Scheme
Latest Construction News
25/11/2024
Estilo Interiors has been selected to help Bruntwood SciTech as they invest a further £2.4 million into Birmingham as part of a plan to transform its Mclaren innovation hub. The project, located less than five minutes' walk from the future HS2 Curzon Street Station, will involve the building ...
25/11/2024
Cambridge Investment Partnership (CIP) has reached a significant milestone at Aylesborough Close in Arbury, with the completion of a topping-out ceremony. CIP board members, ward councillors, One Public Estate, Homes England and the CIP team gathered to lay the final brick at the highest point of ...
25/11/2024
Lovell has appointed Nicola Colley as head of land in the West Midlands, boosting the business' expertise in land opportunities. Having previously worked at Lovell for 12 years, Nicola has returned to a brand-new role at the national housebuilder, bringing with her experience from Taylor Wimpey ...
25/11/2024
Stepnell has commenced enabling works for a significant £9 million refurbishment of the Grade II listed Town Hall in Hugh Town, located on St Mary's in the Isles of Scilly. Spearheaded by the Council of the Isles of Scilly in partnership with Scilly Arts & Heritage, the project marks a pivotal ...
25/11/2024
Morgan Sindall Construction has successfully completed the restoration of West Bromwich Town Hall and Library, restoring the significant building to its former glory for the community to enjoy. Prior to the project's handover, Morgan Sindall gave a presentation to the SMBC Members and Town ...
25/11/2024
Persimmon Homes Severn Valley has donated 10,000 bricks to AccXel, the Construction Skills Accelerator Centre in Cinderford. The contribution will enable students at the Gloucestershire-based facility to gain hands-on experience and develop essential skills for the construction industry. The ...
25/11/2024
Nearly a year after work began, significant progress is being made at Huddersfield station as part of the Transpennine Route Upgrade (TRU). This transformative project aims to modernise the key northern transport hub while preserving its rich heritage as a Grade I listed building. One of the ...
25/11/2024
Renovating a property can be a challenging and complex process, especially when integrating new and existing building elements. At R Elliott Associates Ltd, we specialise in helping clients navigate these challenges by providing expert planning, design, and support to pre-empt any potential ...
25/11/2024
Northumbrian Water has announced a significant investment of £3.5 million at its Great Ayton Sewage Treatment Works (STW) to enhance its capacity to manage stormwater. The project involves the installation of a new storm tank capable of holding up to 317 cubic meters of combined rainwater and ...
25/11/2024
Balfour Beatty Flannery, a partnership between Balfour Beatty and Flannery Plant Hire, has trained its 1,000th student at its Operator Skills Hub. With over 250,000 additional workers needed in the construction industry by 2028, Balfour Beatty Flannery's Operator Skills Hub is key in addressing ...