Work on a new £24 million bypass in Lancashire has been delayed until early next year, it has been announced.
The Broughton Bypass project is being delivered by Hochtief UK, on behalf of Lancashire County Council. However, work is not expected to be finished until early 2018.
The local authority said the delay is down to a number of reasons, such as the utility contractor being unable to carry out work on the site as planned, the rebuilding of an embankment which collapsed due to extremely wet ground conditions, redesigned drainage to accommodate underground equipment, and more challenging ground conditions than expected.
In addition, the delays has affected the overall cost of the scheme with the total now estimated at £32m.
The scheme aims to reduce traffic travelling through the centre of Broughton on Garstang Road by up to 90% and improve journey times into and out of Preston. It will also create better connectivity to the wider road network, with benefits to the development and economic growth of the local area.
County Councillor Keith Iddon said: "We share people's frustrations at these delays and apologise for the disruption it has been causing to people's homes, businesses and journeys.
"We're clearly disappointed that there has been a further delay to this scheme, and look forward to seeing the final stages completed.
"We're working with the contractors, Hochtief, to do everything that we can to minimise the inconvenience while this major build takes place.
"It's a big challenge to construct a major road such as the bypass, with the A6 carrying a lot of traffic and few options for alternative routes, which would allow us to close roads for longer as part of the work.
"It's been many decades since this road was first considered and the reality is that despite the delays, in a few months we will have a new bypass which will bring much-needed congestion relief to the village itself and the wider area. Great progress has already been made and a lot of construction work has been done which people may not be able to see from the road."
(LM)
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
25/11/2024
Estilo Interiors has been selected to help Bruntwood SciTech as they invest a further £2.4 million into Birmingham as part of a plan to transform its Mclaren innovation hub. The project, located less than five minutes' walk from the future HS2 Curzon Street Station, will involve the building ...
25/11/2024
Cambridge Investment Partnership (CIP) has reached a significant milestone at Aylesborough Close in Arbury, with the completion of a topping-out ceremony. CIP board members, ward councillors, One Public Estate, Homes England and the CIP team gathered to lay the final brick at the highest point of ...
25/11/2024
Lovell has appointed Nicola Colley as head of land in the West Midlands, boosting the business' expertise in land opportunities. Having previously worked at Lovell for 12 years, Nicola has returned to a brand-new role at the national housebuilder, bringing with her experience from Taylor Wimpey ...
25/11/2024
Stepnell has commenced enabling works for a significant £9 million refurbishment of the Grade II listed Town Hall in Hugh Town, located on St Mary's in the Isles of Scilly. Spearheaded by the Council of the Isles of Scilly in partnership with Scilly Arts & Heritage, the project marks a pivotal ...
25/11/2024
Morgan Sindall Construction has successfully completed the restoration of West Bromwich Town Hall and Library, restoring the significant building to its former glory for the community to enjoy. Prior to the project's handover, Morgan Sindall gave a presentation to the SMBC Members and Town ...
25/11/2024
Persimmon Homes Severn Valley has donated 10,000 bricks to AccXel, the Construction Skills Accelerator Centre in Cinderford. The contribution will enable students at the Gloucestershire-based facility to gain hands-on experience and develop essential skills for the construction industry. The ...
25/11/2024
Nearly a year after work began, significant progress is being made at Huddersfield station as part of the Transpennine Route Upgrade (TRU). This transformative project aims to modernise the key northern transport hub while preserving its rich heritage as a Grade I listed building. One of the ...
25/11/2024
Renovating a property can be a challenging and complex process, especially when integrating new and existing building elements. At R Elliott Associates Ltd, we specialise in helping clients navigate these challenges by providing expert planning, design, and support to pre-empt any potential ...
25/11/2024
Northumbrian Water has announced a significant investment of £3.5 million at its Great Ayton Sewage Treatment Works (STW) to enhance its capacity to manage stormwater. The project involves the installation of a new storm tank capable of holding up to 317 cubic meters of combined rainwater and ...
25/11/2024
Balfour Beatty Flannery, a partnership between Balfour Beatty and Flannery Plant Hire, has trained its 1,000th student at its Operator Skills Hub. With over 250,000 additional workers needed in the construction industry by 2028, Balfour Beatty Flannery's Operator Skills Hub is key in addressing ...