Highways England has revealed the innovative technique used to install two bridges in one weekend as part of work to upgrade the A14.
"How do you build two 1,000 tonne bridges over a very busy road while (nearly) keeping the road open throughout? You build them at the side of the road and wheel them into place at the end!"
This is exactly what the A14 Cambridge to Huntingdon upgrade team has been doing over the past few months. They have built four abutments to support the new bridges as well as two bridge decks at the side of the live carriageway, and are now ready to wheel the bridges decks, each measuring 44 metres, into place on top of the abutments.
Now the team has released an engineering video to show exactly how they plan to tackle the challenge – and it involves a very big, remote controlled platform on wheels.
The new bridges, which are being built as part of the £1.5 billion major improvement scheme and will be located at Bar Hill, will be installed during the weekend of 14 September. They will form a new, improved Bar Hill junction which will connect the A14 to the future local access road between Cambridge and Huntingdon, as well as to the existing local road between Bar Hill and Longstanton (B1050).
David Bray, project director for the A14 Cambridge to Huntingdon upgrade at Highways England, said: "Redesigning and building the Bar Hill junction was identified from the start of the project as one of the main challenges we would have to tackle. I am delighted that we've found a way to build the two bridges while keeping the A14 open as much as possible and disruption for people locally and road users to a minimum. And I am also excited that we're using such an innovative solution to our challenge – that's what makes my job so interesting."
To carry out the bridge deck installation work safely, the A14 will need to be closed between Friday 14 September, 9pm, and Monday 17 September, 6am.
During the closure, clearly signed diversions will be in place as traffic not needing to enter or exit the A14 at Bar Hill will not be able to travel through the junction along the A14 in either direction.
Through traffic travelling eastbound toward Cambridge will be diverted to leave the A14 at Godmanchester (junction 24), follow the diversion via the A1198, and A428. Through traffic travelling westbound toward Huntingdon will follow the same diversion in reverse.
The team will also need to make some temporary changes to the slip road during the closure.
Traffic wishing to travel westbound from Bar Hill will be able to access the A14 towards Huntingdon but it won't be possible to travel eastbound on the A14 from Bar Hill. Traffic wishing to travel eastbound will be diverted via the westbound A14 to Godmanchester and join the through traffic diversion towards Cambridge.
The new bridges will ultimately replace the old bridge which will be demolished in 2019.
To help people find out more about this work and the closures, the A14 upgrade team will be available with their Mobile Visitor Centre at Tesco Bar Hill on Monday 03 September, 4pm to 8pm and Thursday 06 September, 4pm to 8pm.
There is no space to safely watch the work taking place during the weekend, but people can find out more about the work and closure details, and watch the work via a live stream online by visiting the A14 Cambridge to Huntingdon social media channels and website.
Highways England is upgrading a 21-mile stretch of the A14 between Cambridge and Huntingdon to three lanes in each direction including a brand new 17-mile bypass south of Huntingdon, with four lanes in each direction between Bar Hill and Girton. The project, which includes 34 bridges and main structures, will add additional capacity, boost the local and national economy and cut up to 20 minutes off journeys.
(MH/CM)
Time and date
CONSTRUCTION DIRECTORY
Construction News
03/09/2018
Highways England Unveils Innovative Technique Used On Bridge Installation
Latest Construction News
25/11/2024
Estilo Interiors has been selected to help Bruntwood SciTech as they invest a further £2.4 million into Birmingham as part of a plan to transform its Mclaren innovation hub. The project, located less than five minutes' walk from the future HS2 Curzon Street Station, will involve the building ...
25/11/2024
Cambridge Investment Partnership (CIP) has reached a significant milestone at Aylesborough Close in Arbury, with the completion of a topping-out ceremony. CIP board members, ward councillors, One Public Estate, Homes England and the CIP team gathered to lay the final brick at the highest point of ...
25/11/2024
Lovell has appointed Nicola Colley as head of land in the West Midlands, boosting the business' expertise in land opportunities. Having previously worked at Lovell for 12 years, Nicola has returned to a brand-new role at the national housebuilder, bringing with her experience from Taylor Wimpey ...
25/11/2024
Stepnell has commenced enabling works for a significant £9 million refurbishment of the Grade II listed Town Hall in Hugh Town, located on St Mary's in the Isles of Scilly. Spearheaded by the Council of the Isles of Scilly in partnership with Scilly Arts & Heritage, the project marks a pivotal ...
25/11/2024
Morgan Sindall Construction has successfully completed the restoration of West Bromwich Town Hall and Library, restoring the significant building to its former glory for the community to enjoy. Prior to the project's handover, Morgan Sindall gave a presentation to the SMBC Members and Town ...
25/11/2024
Persimmon Homes Severn Valley has donated 10,000 bricks to AccXel, the Construction Skills Accelerator Centre in Cinderford. The contribution will enable students at the Gloucestershire-based facility to gain hands-on experience and develop essential skills for the construction industry. The ...
25/11/2024
Nearly a year after work began, significant progress is being made at Huddersfield station as part of the Transpennine Route Upgrade (TRU). This transformative project aims to modernise the key northern transport hub while preserving its rich heritage as a Grade I listed building. One of the ...
25/11/2024
Renovating a property can be a challenging and complex process, especially when integrating new and existing building elements. At R Elliott Associates Ltd, we specialise in helping clients navigate these challenges by providing expert planning, design, and support to pre-empt any potential ...
25/11/2024
Northumbrian Water has announced a significant investment of £3.5 million at its Great Ayton Sewage Treatment Works (STW) to enhance its capacity to manage stormwater. The project involves the installation of a new storm tank capable of holding up to 317 cubic meters of combined rainwater and ...
25/11/2024
Balfour Beatty Flannery, a partnership between Balfour Beatty and Flannery Plant Hire, has trained its 1,000th student at its Operator Skills Hub. With over 250,000 additional workers needed in the construction industry by 2028, Balfour Beatty Flannery's Operator Skills Hub is key in addressing ...