The iconic Nene Bridge in Peterborough has been strengthened in a landmark project.
Contractor Skanska delivered a unique reinforced concrete encasement for V-shaped piers to extend the life of the bridge. This is the first project of its kind in the UK.
The project involved strengthening six of the eight piers supporting the Nene Bridge, a 155m long structure carrying more than 60,000 vehicles daily.
Work was completed on the project a month ahead of schedule despite significant challenges like its complex architectural design and working in close proximity to a live railway line.
The team used hundreds of steel bars to wrap each of the unique piers, creating complex reinforced concrete jackets that supplement the unique geometry of the structure.
As two of the piers requiring strengthening were positioned within the River Nene, a temporary coffer dam was built to provide access below the water level.
Moving the heavy formwork panels from one pier to another with restricted headroom could mean a lengthy and expensive process of dismantling and rebuilding them. The team used an air skid system – placing air skid pads under the formwork and skating it into its new
position on 2mm of air – to achieve time and cost savings of 90% and 70% respectively.
The team also used digital tools throughout the project, creating 3D printed models of the four stages of construction of the bridge piers; existing pier, pier following hydrodemolition, first concrete pour, and completed encasement to visualise the geometry of the complex, multifaceted structure.
Mark Shopland, Operations Director, said: "This was a technically challenging project that gave us a great opportunity to utilise our wide spectrum of expertise from across our construction and design teams, working collaboratively with our supply chain. We were also able to use the latest engineering technology to deliver an innovative solution to a significant challenge faced by our valued customer, all the while preserving the distinctive appearance of this iconic bridge for another 50 years without any road closures."
This refurbishment project was carried out on behalf of Peterborough City Council.
(CM/JG)
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
29/11/2024
Helmsley Group secured planning permission for the final part of its Coney Street Riverside masterplan which will bring much needed residential space to the city and realise a 50-year ambition to reconnect York to its riverfront. With work expected to start in the summer of 2025, this approval ...
29/11/2024
Network Space Developments (NSD) has received planning approval from Manchester City Council for a major redevelopment project at its Welcomb Street site in Openshaw, Manchester. The four-acre site, acquired by NSD in 2022, will be transformed into an extension of the adjacent City Works Business ...
29/11/2024
Work has commenced on a new lighting scheme designed to create brighter streets in Digbeth, close to HS2's Birmingham Curzon Street station. The Birmingham City Council project – funded in part through a £210,140 investment from HS2's Business and Local Economy Fund (BLEF) – will see the ...
29/11/2024
Building work has commenced on 14 new modern one-bedroom apartments at Ludwick Green in Welwyn Garden City. The apartments are being developed as part of Welwyn Hatfield Borough Council's (WHBC) Affordable Housing Programme, and its commitment to building new social and affordable homes. Ludwick ...
29/11/2024
River Capital has invested £500,000 in Liverpool-based M&E engineering consultancy, Steven A Hunt & Associates Ltd. The funding was structured to facilitate a management buyout (MBO) by the senior management team of Neil Baines, Anne King, Dave Kelly and Dominic Sibbring from founder Steven Hunt, ...
29/11/2024
Henley Restoration and Remedials has been chosen to carry out extensive external and structural repairs on the Grade II-listed Phoenix Mill, the oldest building in the Rutland Mills complex. Originally a grain store, Phoenix Mill later became a corn mill in the 19th century before transitioning ...
29/11/2024
Dorset County Council's North East Technology Park (NETPark) has been allocated over £11 million towards its expansion. The North East Combined Authority's Cabinet has approved £11.3m of funding for the Sedgefield site from its £160m flagship North East Investment Zone (NEIZ), which aims to drive ...
29/11/2024
Laing O'Rourke, in collaboration with Barnsley College and T3 Training & Development, have opened the UK's first dedicated modern methods of construction (MMC) training facility. The first of its kind training centre represents a groundbreaking step in addressing the UK's construction skills ...
29/11/2024
Aqua Direct are keen to share their support for the Urgent Funding campaign from St Giles Hospice. With a national hospice funding crisis, they need your support more than ever ...
29/11/2024
As we approach the end of 2024, we have been reflecting on what an action-packed year it has been. We have worked with some fantastic clients and sites across the country. We started from our base in Essex over ten years ago, and the demand for trackway has certainly been at its highest ...