HS2 Establishes Rebar Threading Facility

Construction News Image
HS2 has established a rebar threading facility to address materials shortages at its Copthall tunnel construction site in Hillingdon - creating jobs, cutting waste and reducing lorry movements.

The new facility will make 92,000 rebar couplers, needed to construct the Copthall tunnel.

The Skanska Costain STRABAG joint venture (SCS JV) team constructing the tunnel were faced with delays due to a shortfall of available prefabricated fatigue rated rebar couplers, after suppliers had exited the market. To address this, the team has constructed a threading facility on site to produce the required quantities of the materials themselves.

As well as addressing supply shortfall, the threading facility has resulted in a significant financial saving on the project by reducing waste, costs and lorry movements, and overall creating a more efficient way of working.

-- Advertisement --
hss

To construct the 880 metre long cut and cover Copthall tunnel, 92,000 fatigue rated couplers are required. A team of 14 will work at the facility six days a week, 8 hours a day for three years to meet the supply needs for the tunnel.

The process to get the facility up and running took 20 weeks in total, with the team gaining CARES certification (assured certification for the constructional steels industry) for the work and securing the required equipment from Sheffield based company, Leviat. It is only the second time CARES certification has been given for this activity to happen onsite.

The team purchase stock rebar and then complete processing operations on site, before taking it through the four-step threading process and delivering it to the Copthall tunnel construction area. All the work is taking place within the site boundary reducing unnecessary lorry movements, supporting HS2 Net Zero Carbon targets.

The solution was devised by Ray Moloney, Senior Project Manager for SCS JV, who explains his approach: "Uncertainties in the market and the need to meet the requirements of the HS2 construction programme meant that we had to look at an innovative solution for supplying fatigue rated mechanical reinforcement connections. In mid-2022 we started engaging with partners including Leviat and CARES to develop an on-site processing scheme and within 20 weeks, we were processing our first order.

"The solution has created new jobs, offered new training opportunities for engineers and means that we can remove the risk of any delays in construction due to supply shortages."

Latest Construction News

25/11/2024

Estilo Interiors has been selected to help Bruntwood SciTech as they invest a further £2.4 million into Birmingham as part of a plan to transform its Mclaren innovation hub. The project, located less than five minutes' walk from the future HS2 Curzon Street Station, will involve the building ...
25/11/2024

Cambridge Investment Partnership (CIP) has reached a significant milestone at Aylesborough Close in Arbury, with the completion of a topping-out ceremony. CIP board members, ward councillors, One Public Estate, Homes England and the CIP team gathered to lay the final brick at the highest point of ...
25/11/2024

Lovell has appointed Nicola Colley as head of land in the West Midlands, boosting the business' expertise in land opportunities. Having previously worked at Lovell for 12 years, Nicola has returned to a brand-new role at the national housebuilder, bringing with her experience from Taylor Wimpey ...
25/11/2024

Stepnell has commenced enabling works for a significant £9 million refurbishment of the Grade II listed Town Hall in Hugh Town, located on St Mary's in the Isles of Scilly. Spearheaded by the Council of the Isles of Scilly in partnership with Scilly Arts & Heritage, the project marks a pivotal ...
25/11/2024

Morgan Sindall Construction has successfully completed the restoration of West Bromwich Town Hall and Library, restoring the significant building to its former glory for the community to enjoy. Prior to the project's handover, Morgan Sindall gave a presentation to the SMBC Members and Town ...
25/11/2024

Persimmon Homes Severn Valley has donated 10,000 bricks to AccXel, the Construction Skills Accelerator Centre in Cinderford. The contribution will enable students at the Gloucestershire-based facility to gain hands-on experience and develop essential skills for the construction industry. The ...
25/11/2024

Nearly a year after work began, significant progress is being made at Huddersfield station as part of the Transpennine Route Upgrade (TRU). This transformative project aims to modernise the key northern transport hub while preserving its rich heritage as a Grade I listed building. One of the ...
25/11/2024

Renovating a property can be a challenging and complex process, especially when integrating new and existing building elements. At R Elliott Associates Ltd, we specialise in helping clients navigate these challenges by providing expert planning, design, and support to pre-empt any potential ...
25/11/2024

Northumbrian Water has announced a significant investment of £3.5 million at its Great Ayton Sewage Treatment Works (STW) to enhance its capacity to manage stormwater. The project involves the installation of a new storm tank capable of holding up to 317 cubic meters of combined rainwater and ...
25/11/2024

Balfour Beatty Flannery, a partnership between Balfour Beatty and Flannery Plant Hire, has trained its 1,000th student at its Operator Skills Hub. With over 250,000 additional workers needed in the construction industry by 2028, Balfour Beatty Flannery's Operator Skills Hub is key in addressing ...
Efco UK LtdLakeside HireBRICOFLOR UKStuart CanvasT & D Glazing And Installation LimitedThink Construction Skills Ltd.Aqua Direct LtdAtlas Winch & Hoist Services Ltd (UK)Landscaping CambridgeMy Thread Curtains
Terms and Conditions
2024/11/26 11:49:58