07/08/2023

Engineers Urgently Redesign Warwick Station Upgrades

Construction News Image
Network Rail engineers are urgently redesigning Warwick station's multi-million-pound accessibility upgrades after an unexpected discovery which forced work to stop.

Network Rail was midway through the work to install new lift shafts down into the station's subway to provide step-free access to both platforms for the first time.

However, workers have found unexpected foundations believed to be from the first railway station built on the site in 1852, which lasted just 42 years before being destroyed by fire in 1894.

Unbeknown to the engineers, as it wasn't recorded in the plans of what was then rebuilt 129 years ago, the current building is constructed on top of the original station's 1852 foundations.

-- Advertisement --
hss

The unexpected walls lie right where the lifts were due to go, and the substructure can’t be disturbed as it is integral to the existing building and platform.

It means new detailed designs now have to be drawn up for the lift shafts, pausing the building work for the time being.

Due to construction inside the subway is well underway, it will have to stay closed with the diversionary walking route staying in place for passengers.

People are being urged to use this route correctly, with incidents of people trespassing across the tracks to get between platforms still causing safety concerns.

Elinor Weymouth, scheme project manager for Network Rail, said: "We know how much the accessibility upgrades mean to people in Warwick and we’re sorry this unexpected setback means the building work has to be paused.

"We are committed to delivering this vital work so the station is accessible for everyone, and are working hard to get new plans drawn up and workers back on site as soon as we possibly can.

"I want to thank passengers for their patience while this work goes on behind the scenes and urge everyone to continue to follow the walking diversion that’s in place while the subway is closed."



Latest Construction News

29/11/2024

Helmsley Group secured planning permission for the final part of its Coney Street Riverside masterplan which will bring much needed residential space to the city and realise a 50-year ambition to reconnect York to its riverfront. With work expected to start in the summer of 2025, this approval ...
29/11/2024

Network Space Developments (NSD) has received planning approval from Manchester City Council for a major redevelopment project at its Welcomb Street site in Openshaw, Manchester. The four-acre site, acquired by NSD in 2022, will be transformed into an extension of the adjacent City Works Business ...
29/11/2024

Work has commenced on a new lighting scheme designed to create brighter streets in Digbeth, close to HS2's Birmingham Curzon Street station. The Birmingham City Council project – funded in part through a £210,140 investment from HS2's Business and Local Economy Fund (BLEF) – will see the ...
29/11/2024

Building work has commenced on 14 new modern one-bedroom apartments at Ludwick Green in Welwyn Garden City. The apartments are being developed as part of Welwyn Hatfield Borough Council's (WHBC) Affordable Housing Programme, and its commitment to building new social and affordable homes. Ludwick ...
29/11/2024

River Capital has invested £500,000 in Liverpool-based M&E engineering consultancy, Steven A Hunt & Associates Ltd. The funding was structured to facilitate a management buyout (MBO) by the senior management team of Neil Baines, Anne King, Dave Kelly and Dominic Sibbring from founder Steven Hunt, ...
29/11/2024

Henley Restoration and Remedials has been chosen to carry out extensive external and structural repairs on the Grade II-listed Phoenix Mill, the oldest building in the Rutland Mills complex. Originally a grain store, Phoenix Mill later became a corn mill in the 19th century before transitioning ...
29/11/2024

Dorset County Council's North East Technology Park (NETPark) has been allocated over £11 million towards its expansion. The North East Combined Authority's Cabinet has approved £11.3m of funding for the Sedgefield site from its £160m flagship North East Investment Zone (NEIZ), which aims to drive ...
29/11/2024

Laing O'Rourke, in collaboration with Barnsley College and T3 Training & Development, have opened the UK's first dedicated modern methods of construction (MMC) training facility. The first of its kind training centre represents a groundbreaking step in addressing the UK's construction skills ...
29/11/2024

Aqua Direct are keen to share their support for the Urgent Funding campaign from St Giles Hospice. With a national hospice funding crisis, they need your support more than ever ...
29/11/2024

As we approach the end of 2024, we have been reflecting on what an action-packed year it has been. We have worked with some fantastic clients and sites across the country. We started from our base in Essex over ten years ago, and the demand for trackway has certainly been at its highest ...
Think Construction Skills Ltd.Efco UK LtdT & D Glazing And Installation LimitedBRICOFLOR UKAqua Direct LtdLakeside HireStuart CanvasCabin MasterSussex Window WorksA1 Grab Hire
Terms and Conditions
2024/11/29 22:10:23