Engineers at Network Rails have completed improvement works between Yeovil Pen Mill and Weymouth.
The railway re-opened as planned on Saturday, 21 October, following the line being closed from Monday 16 to Friday 20 October, during which buses replaced Great Western Railway (GWR) trains.
During the five days the railway was closed, Network Rail's team worked to replace 758 metres of outdated 1950s track between Maiden Newton and Chetnole in Cattistock. The old-style track needed to be renewed and brought up to modern standards to help reduce the number of speed restrictions that are put in place during warmer weather, helping ensure customers enjoy smoother and more reliable journeys in the future.
Network Rail took advantage of the extended line closure to maximise the amount of work that could be achieved, completing a number of other improvements to the railway including erecting scaffolding at Evershot tunnel to repair and repoint the brickwork.
This latest work follows two back-to-back five-day closures earlier this year in February and March between Castle Cary/Yeovil Pen Mill and Weymouth during which a range of work was completed, including:
• Renewing over 1,800 metres of track through Thornford station and replacing old wooden sleepers with new, more durable concrete sleepers.
• Refurbishing Maiden Newton station including repairing the canopies and giving the station building a fresh lick of paint.
• Installing new tactile paving at Yeovil Pen Mill station.
• Clearing overgrown vegetation and completing maintenance on key pieces of railway infrastructure along the line.
Oliver Frost, Network Rail project director, said: "I'd like to thank customers and local residents for their patience and understanding last week while we closed the railway between Yeovil Pen Mill and Weymouth to allow our engineers to complete a range of key upgrades to the Heart of Wessex line.
"We know how important this stretch of railway is and last week's upgrades are the latest efforts in a three-year period in which we’ve invested a significant amount to bring smoother and more reliable journeys for our customers travelling between Somerset and Dorset
"We recognise many customers will have been disrupted during last week’s extended closure for which we’re sorry. However, these slightly longer closures enable us to really maximise the opportunity to complete a wide range of upgrades in a more cost-effective way while reducing the need for the need for regular, smaller closures of the railway which would be more disruptive to customers."
Time and date
CONSTRUCTION DIRECTORY
Construction News
23/10/2023
Railway Improvement Works Complete Between Yeovil Pen Mill And Weymouth
Latest Construction News
29/11/2024
Helmsley Group secured planning permission for the final part of its Coney Street Riverside masterplan which will bring much needed residential space to the city and realise a 50-year ambition to reconnect York to its riverfront. With work expected to start in the summer of 2025, this approval ...
29/11/2024
Network Space Developments (NSD) has received planning approval from Manchester City Council for a major redevelopment project at its Welcomb Street site in Openshaw, Manchester. The four-acre site, acquired by NSD in 2022, will be transformed into an extension of the adjacent City Works Business ...
29/11/2024
Work has commenced on a new lighting scheme designed to create brighter streets in Digbeth, close to HS2's Birmingham Curzon Street station. The Birmingham City Council project – funded in part through a £210,140 investment from HS2's Business and Local Economy Fund (BLEF) – will see the ...
29/11/2024
Building work has commenced on 14 new modern one-bedroom apartments at Ludwick Green in Welwyn Garden City. The apartments are being developed as part of Welwyn Hatfield Borough Council's (WHBC) Affordable Housing Programme, and its commitment to building new social and affordable homes. Ludwick ...
29/11/2024
River Capital has invested £500,000 in Liverpool-based M&E engineering consultancy, Steven A Hunt & Associates Ltd. The funding was structured to facilitate a management buyout (MBO) by the senior management team of Neil Baines, Anne King, Dave Kelly and Dominic Sibbring from founder Steven Hunt, ...
29/11/2024
Henley Restoration and Remedials has been chosen to carry out extensive external and structural repairs on the Grade II-listed Phoenix Mill, the oldest building in the Rutland Mills complex. Originally a grain store, Phoenix Mill later became a corn mill in the 19th century before transitioning ...
29/11/2024
Dorset County Council's North East Technology Park (NETPark) has been allocated over £11 million towards its expansion. The North East Combined Authority's Cabinet has approved £11.3m of funding for the Sedgefield site from its £160m flagship North East Investment Zone (NEIZ), which aims to drive ...
29/11/2024
Laing O'Rourke, in collaboration with Barnsley College and T3 Training & Development, have opened the UK's first dedicated modern methods of construction (MMC) training facility. The first of its kind training centre represents a groundbreaking step in addressing the UK's construction skills ...
29/11/2024
Aqua Direct are keen to share their support for the Urgent Funding campaign from St Giles Hospice. With a national hospice funding crisis, they need your support more than ever ...
29/11/2024
As we approach the end of 2024, we have been reflecting on what an action-packed year it has been. We have worked with some fantastic clients and sites across the country. We started from our base in Essex over ten years ago, and the demand for trackway has certainly been at its highest ...